Der Vortrag „PRINCE2 Agile® Practitioner: Sample Exam (2)“ von Dion Training ist Bestandteil des Kurses „PRINCE2 Agile® – Practitioner 6th Edition including Exam (EN)“.
How is timeboxing typically described? (Copyright © AXELOS Limited 2018, usage approved by AXELOS Limited. All rights reserved.)
Which characteristic is MOST likely to apply to a project using PRINCE2 Agile? (Copyright © AXELOS Limited 2018, usage approved by AXELOS Limited. All rights reserved.)
Which describes an agile approach which can be integrated with PRINCE2 Agile? (Copyright © AXELOS Limited 2018, usage approved by AXELOS Limited. All rights reserved.)
Which aspect of a traditional project management approach is necessary when PRINCE2 Agile is applied? (Copyright © AXELOS Limited 2018, usage approved by AXELOS Limited. All rights reserved.)
Which statement accurately reflects one of the eight guidance points? (Copyright © AXELOS Limited 2018, usage approved by AXELOS Limited. All rights reserved.)
Which aspect of PRINCE2 benefits MOST from blending with Agile? (Copyright © AXELOS Limited 2018, usage approved by AXELOS Limited. All rights reserved.)
Using the Project Scenario and Rebranding Additional information, answer the following question: Brand-u-Like has been given the following quality criteria for the new letterheads they are working on: • Must adhere to the corporate image; • No spelling or grammatical errors; • Should be printable in black and white as well as colour to enable cheaper printing, if required. Which PRINCE2 principle is being applied? (Copyright © AXELOS Limited 2018, usage approved by AXELOS Limited. All rights reserved.)
Using the Project Scenario and Rebranding Additional information, answer the following question: It has been recommended that a marketing campaign be used to determine whether the proposed new corporate logo is sufficiently unique and recognizable. This campaign will target a non-English speaking country. How effectively does this apply the ‘continued business justification’ principle? (Copyright © AXELOS Limited 2018, usage approved by AXELOS Limited. All rights reserved.)
Using the Project Scenario and Rebranding Additional information, answer the following question: During the initiation stage, the business case is being refined and the project plan is being produced. The following risk cause is identified: ‘The marketing campaign and website delivery are both dependent on the timely delivery of the corporate logo to the defined level of quality.’ How should the business case theme be tailored as a result of this risk cause? (Copyright © AXELOS Limited 2018, usage approved by AXELOS Limited. All rights reserved.)
Using the Project Scenario and Rebranding Additional information, answer the following question: Brand-u-Like is working on the ‘Collateral’ work package in Stage 2 and has agreed the priorities for each of the requirements. Brand-u-Like believes that it is unlikely that all of the requirements will be delivered during the timebox as some of them are still being explored. Brand-u-Like is keen to become more agile and responsive in the way they work with Chesterstons. How should Brand-u-Like monitor progress to tailor the progress theme? (Copyright © AXELOS Limited 2018, usage approved by AXELOS Limited. All rights reserved.)
Using the Project Scenario and Rebranding Additional information, answer the following question: Brand-u-Like has created a risk register on its team board. It is updated during daily stand-ups as the risks associated with delivering the corporate logo are discussed. Brand-u-Like is finding this agile way of working to be very effective in monitoring risks associated with the work package. The team manager sends photographs of the team board to the project manager daily. The project manager uses this information in order to review the work package status. What BEST explains how this approach to risk management tailors the risk theme? (Copyright © AXELOS Limited 2018, usage approved by AXELOS Limited. All rights reserved.)
Using the Project Scenario and Rebranding Additional information, answer the following question: During Brand-u-Like’s daily stand-up, a rumour that the supplier of the banners may be about to become insolvent was reported. As a result, it was agreed that a safe-to-fail experiment should be conducted. This will determine whether Brand-u-Like could complete the work of adding an extra logo to the banners themselves if necessary. How effectively does the use of the safe-to-fail experiment apply the risk theme? (Copyright © AXELOS Limited 2018, usage approved by AXELOS Limited. All rights reserved.)
Using the Project Scenario and Rebranding Additional information, answer the following question: During the ‘starting up a project’ process, the following statement is captured: ‘It is expected that Brand-u-Like will act in a more agile way than they have in the past with the use of MoSCoW prioritization and with a greater focus on collaboration.’ Where should this statement be recorded as part of the ‘starting up a project’ process? (Copyright © AXELOS Limited 2018, usage approved by AXELOS Limited. All rights reserved.)
Using the Project Scenario and Rebranding Additional information, answer the following question: Brand-u-Like is delivering the corporate clothing designs as part of the ‘Collateral’ work package. The current plan is for the actual clothing to be delivered (by an external supplier) at the end of week 14. Brand-u-Like has been advised by the executive that a set of rebranded corporate clothing is required before week 14, so that it can be worn by the staff attending the International Cheese Festival. Which is the BEST way for the project manager to respond in order to tailor the ‘controlling a stage’ process? (Copyright © AXELOS Limited 2018, usage approved by AXELOS Limited. All rights reserved.)
Using the Project Scenario and Rebranding Additional information, answer the following question: The project manager is using Brand-u-Like’s burn-up chart to track progress. How effectively does this apply the PRINCE2 Agile guidance when tailoring the ‘managing product delivery’ process? (Copyright © AXELOS Limited 2018, usage approved by AXELOS Limited. All rights reserved.)
Using the Project Scenario and Rebranding Additional information, answer the following question: It is reported during Brand-u-Like’s daily stand-up that the executive is insisting that rebranded corporate clothing is worn by staff attending the International Cheese Festival. The team believes that the new logo cannot be made available to the clothing manufacturer in time. Therefore, the branded clothing will not be available for the festival. Which is the BEST way for Brand-u-Like to respond? (Copyright © AXELOS Limited 2018, usage approved by AXELOS Limited. All rights reserved.)
Using the Project Scenario and Rebranding Additional information, answer the following question: There are two work packages within the Rebranding work stream. Each work package will be managed as a separate timebox. The ‘Rebranding’ work packages will form a release. Which statement explains how this approach to planning tailors a work package? (Copyright © AXELOS Limited 2018, usage approved by AXELOS Limited. All rights reserved.)
Using the Project Scenario and Rebranding Additional information, answer the following question: In an attempt to adopt a more agile way of working, Brand-u-Like has proposed replacing formal checkpoint reports with daily stand-ups, where team members will take turns to ‘report’ the team’s progress to the project manager. How effectively does this tailor the use of a checkpoint report? (Copyright © AXELOS Limited 2018, usage approved by AXELOS Limited. All rights reserved.)
Using the Project Scenario and Marketing Campaign Additional information, answer the following question: The Marketing Team Manager has confirmed that it will not be possible to complete all of the work involved in the three campaigns planned for Stage 3, where all three campaigns are ‘Must Haves’. The Marketing Director has offered to hire a contractor to assist with the radio campaign. The radio campaign has the following quality criterion: ‘Each advertisement must be at least one minute long, but should be two minutes long.’ How should the Marketing Team apply the ‘protect the level of quality’ target? (Copyright © AXELOS Limited 2018, usage approved by AXELOS Limited. All rights reserved.)
Using the Project Scenario and Marketing Campaign Additional information, answer the following question: During Stage 4, the Marketing Team is due to start work on a series of videos to put on a video sharing website. The release backlog for Stage 4 includes three separate videos as follows: • 'Life is all about cheese!' • 'Chestertons' Blue - How about you?' • Viral video - title and theme to be defined. How should the 'accept that the customer doesn't need everything' target be applied when planning the work of Stage 4? (Copyright © AXELOS Limited 2018, usage approved by AXELOS Limited. All rights reserved.)
Using the Project Scenario and Marketing Campaign Additional information, answer the following question: The Marketing Team has identified the following issue: ‘The newspaper advertisements during Stage 3 have not been as successful as we had hoped. The sales targets for the end of Stage 3 have not been achieved. Therefore, the forecast for the increased sales that must be achieved as a result of the project will no longer be achieved within the planned timescales.’ Which of the ‘six PRINCE2 aspects of a project’ should be immediately assessed as a result of this issue? (Copyright © AXELOS Limited 2018, usage approved by AXELOS Limited. All rights reserved.)
Using the Project Scenario and Marketing Campaign Additional information, answer the following question: The Stage 3 ‘Marketing’ work package includes the following newspaper requirements: • Full-page advertisement - Should Have • Half-page advertisement - Must Have The Marketing Team is running behind schedule and has asked for advice from the project manager. The project manager has requested that the Marketing Team keeps to the time allocated and delivers only the half-page advertisement during the stage. How does this apply the 'being on time and hitting deadlines' target? (Copyright © AXELOS Limited 2018, usage approved by AXELOS Limited. All rights reserved.)
Using the Project Scenario and Marketing Campaign Additional information, answer the following question: The following user story has been defined by the project manager for delivery during Stage 4: ‘As a Chestertons’ sales assistant, I want to see a high quality, successful TV campaign, so that I will receive a bonus for achieving my sales targets.’ No other information has been provided to support this user story. Which reason explains why this is a poor application of the ‘protect the level of quality’ target? (Copyright © AXELOS Limited 2018, usage approved by AXELOS Limited. All rights reserved.)
Using the Project Scenario and Marketing Campaign Additional information, answer the following question: The results of the advertisements carried out during Stage 3 have been analyzed. The social media advertisements were found to be far more effective than expected. The customer subject matter expert (CSME) has recommended that additional social media advertising should replace the planned TV advertising in Stage 4. Which statement BEST describes why the Marketing Team should agree this change in accordance with the ‘five targets’? (Copyright © AXELOS Limited 2018, usage approved by AXELOS Limited. All rights reserved.)
Using the Project Scenario and Marketing Campaign Additional information, answer the following question: There are four people working on the Marketing campaigns. These people have been working in the Marketing Team since the work started. With the recent success of the social media advertising, the Marketing Director has suggested that a social media expert be recruited to work in Stage 4 on additional advertisements. Which statement BEST describes why the Marketing Team should appoint this expert in accordance with the ‘five targets’? (Copyright © AXELOS Limited 2018, usage approved by AXELOS Limited. All rights reserved.)
Using the Project Scenario and Marketing Campaign Additional information, answer the following question: During Stage 3, the first social media advertising is due to be delivered. It was decided that a simple, single-page social media site must be delivered in the first timebox. Information gathered will be used to develop the later campaigns to the defined level of quality. Which statement BEST describes why the Marketing Team should deliver the simple site in accordance with the ‘five targets’? (Copyright © AXELOS Limited 2018, usage approved by AXELOS Limited. All rights reserved.)
Using the Project Scenario and Website Additional information, answer the following question: Web&Go is working on the 'payment' timebox which includes: • Allow payment by credit card - Must Have • Allow payment by debit card - Should Have • Allow payment through an online payment system - Should Have. How should the principle of 'learn from experience' by applied to this work? (Copyright © AXELOS Limited 2018, usage approved by AXELOS Limited. All rights reserved.)
Using the Project Scenario and Website Additional information, answer the following question: Web&Go is delivering the ‘Stock Control’ work package within Stage 4 using a Kanban approach. Chesterton’s IT Team is working on the ‘Story of Cheese’ work package later in the same stage. All requirements have been prioritized using MoSCoW prioritization. A release has been planned at the end of Stage 4 incorporating the outputs of both work packages. Why is this a good application of the ‘manage by stages’ principle? (Copyright © AXELOS Limited 2018, usage approved by AXELOS Limited. All rights reserved.)
Using the Project Scenario and Website Additional information, answer the following question: The IT Team is delivering the ‘Story of Cheese’ work package. This timebox will require some information and advice from the Marketing Team to help with the history of Chesterton’s and the history of cheese. This work will typically take about 2-3 hours daily. How should the Organization theme be tailored to ensure sufficient customer involvement in the IT Team? (Copyright © AXELOS Limited 2018, usage approved by AXELOS Limited. All rights reserved.)
Using the Project Scenario and Website Additional information, answer the following question: The IT Team is delivering the ‘Story of Cheese’ work package. How should the IT Team plan the delivery of this work package to tailor the plans theme? (Copyright © AXELOS Limited 2018, usage approved by AXELOS Limited. All rights reserved.)
Using the Project Scenario and Website Additional information, answer the following question: During Stage 3, the ‘Payment’ work package is being delivered. It includes the requirement to deliver ‘secure payment’. Several user stories have been developed to identify the requirement in more detail. A Web&Go developer has identified that one of the user stories conflicts with one of the acceptance criterion specified in the project product description. The project manager has advised that this change to the project product description can be agreed dynamically with the customer subject matter expert. What BEST explains how this approach tailors the change theme? (Copyright © AXELOS Limited 2018, usage approved by AXELOS Limited. All rights reserved.)
Using the Project Scenario and Website Additional information, answer the following question: Web&Go is delivering the ‘Payment’ work package in Stage 3. A Web&Go developer has written the tests for the payment functionality at the beginning of the timebox. These tests will be used by the team to check that it works correctly. What BEST explains why this ‘test-driven approach’ tailors the Quality theme well? (Copyright © AXELOS Limited 2018, usage approved by AXELOS Limited. All rights reserved.)
Using the Project Scenario and Website Additional information, answer the following question: During the ‘initiating a project’ process, the project office recommended that the project management team should further improve their agile behaviours. The improved behaviours and their value were discussed with the project management team during a workshop. They will be documented in the project initiation documentation (PID). How should the project manager communicate the agreed behaviours to the team? (Copyright © AXELOS Limited 2018, usage approved by AXELOS Limited. All rights reserved.)
Using the Project Scenario and Website Additional information, answer the following question: In Stage 4, work on the ‘Stock Control’ work package is underway. The CSME is unsure of exactly how the notification of low stock should work. Having gathered views from the customer representative and several stock control staff members, the requirement is still unclear. How should the Web&Go make sure that they are delivering what the customer wants? (Copyright © AXELOS Limited 2018, usage approved by AXELOS Limited. All rights reserved.)
Using the Project Scenario and Website Additional information, answer the following question: At the end of Stage 3, the payment timebox is just coming to an end. The project manager is planning to demonstrate the ordering and payment functionality that is being delivered. Several staff from the sales department are attending the demonstration. What BEST explains how this tailors the ‘managing a stage boundary’ process? (Copyright © AXELOS Limited 2018, usage approved by AXELOS Limited. All rights reserved.)
Using the Project Scenario and Website Additional information, answer the following question: During the project kick-off it was agreed how the project management team should work together. The project manager made the following note during the meeting: ‘It is all of our responsibilities to look out for risks. We will raise them as soon as we see them.’ In which management product should this be recorded to formally communicate this agreement? (Copyright © AXELOS Limited 2018, usage approved by AXELOS Limited. All rights reserved.)
Using the Project Scenario and Website Additional information, answer the following question: The project manager was asked to attend a daily stand-up involving the IT Team during Stage 4. The ‘Story of Cheese’ work package was discussed and the project manager wanted to record the agreements reached for future reference. Where should this information be recorded? (Copyright © AXELOS Limited 2018, usage approved by AXELOS Limited. All rights reserved.)
Using the Project Scenario and Website Additional information, answer the following question: The project manager has decided that the benefits management approach should only be checked in the ‘closing a project’ process during Stage 4. It will then be used to measure the increase in sales following the International Cheese Festival. What BEST explains how this tailors the benefits management approach? (Copyright © AXELOS Limited 2018, usage approved by AXELOS Limited. All rights reserved.)
Using the Project Scenario and Move Premises Additional information, answer the following question: The project manager used the Agilometer to assess the agile environment in order to tailor PRINCE2 in the most effective way. Each production line is similar but not exactly the same. Due to an initial plan that moved the current production lines in a specified order, it was observed that the ‘Flexibility on what is being delivered’ slider is low. Which is the MOST appropriate response to this observation? (Copyright © AXELOS Limited 2018, usage approved by AXELOS Limited. All rights reserved.)
Using the Project Scenario and Move Premises Additional information, answer the following question: Moving the production lines one-by-one over a series of timeboxes means that the deliveries of ingredients, packaging and the dispatching of the cheeses will be difficult to coordinate across more than one site. Against which Agilometer slider would it be MOST appropriate to assess the risks as a result of this situation? (Copyright © AXELOS Limited 2018, usage approved by AXELOS Limited. All rights reserved.)
Using the Project Scenario and Move Premises Additional information, answer the following question: The following requirement has been specified as part of the move premises work stream: As a: stock controller I want: to be able to move stock into a stock room Which is the BEST entry for the ‘benefit’ in this user story? (Copyright © AXELOS Limited 2018, usage approved by AXELOS Limited. All rights reserved.)
Using the Project Scenario and Move Premises Additional information, answer the following question: Entrance to the new site is via a narrow access road. There are parking restrictions linked to lorries using this access road. Which requirement is MOST likely to have the lowest priority? (Copyright © AXELOS Limited 2018, usage approved by AXELOS Limited. All rights reserved.)
Using the Project Scenario and Move Premises Additional information, answer the following question: The Marketing Team wants to issue some publicity about each type of cheese as that particular production line is moved over to the new premises. Which is the MOST appropriate way for the Premises Team to communicate timings and progress to the Marketing Team? (Copyright © AXELOS Limited 2018, usage approved by AXELOS Limited. All rights reserved.)
Using the Project Scenario and Move Premises Additional information, answer the following question: According to the frequent releases focus area, which requirement would be MOST useful to deliver early to ensure that the project is viable? (Copyright © AXELOS Limited 2018, usage approved by AXELOS Limited. All rights reserved.)
Using the Project Scenario and Move Premises Additional information, answer the following question: The project manager is using the Agilometer to assess the prevailing agile environment in order to tailor PRINCE2 in the most effective way. Some of the Move Premises Team are positive about agile but are unsure how it can be used for the production lines. They are dedicated to the project and are constructive in team meetings when expressing their opinions, but they are insisting that a ‘specify, design, build and test’ approach is adhered to. Which slider should be set lower for the reason given? (Copyright © AXELOS Limited 2018, usage approved by AXELOS Limited. All rights reserved.)
Using the Project Scenario and Move Premises Additional information, answer the following question: Which characteristic justifies a low-level setting for the ‘Ability to work iteratively and deliver incrementally’ slider on the Agilometer for this part of the project? (Copyright © AXELOS Limited 2018, usage approved by AXELOS Limited. All rights reserved.)
Using the Project Scenario and Move Premises Additional information, answer the following question: During Stage 2, the following user story has been developed as part of the P1 work package: As a: delivery van loader I want to: know the weight of any box So that: I can avoid injury. Which explains how this user story could be improved? (Copyright © AXELOS Limited 2018, usage approved by AXELOS Limited. All rights reserved.)
Using the Project Scenario and Move Premises Additional information, answer the following question: During the P1 timebox, a requirement is identified for the post room dispatcher to know the weight of parcels to calculate the correct postage. During the timebox, an additional requirement was identified for a warning label to be fixed to heavy parcels needing more than one person to lift them safely. Which action is the BEST way of addressing this change to the requirements? (Copyright © AXELOS Limited 2018, usage approved by AXELOS Limited. All rights reserved.)
Using the Project Scenario and Move Premises Additional information, answer the following question: During the premises move it has been difficult to hold the daily stand-ups. Some teleconferences have been held but attendance at these has been varied. The team is now experimenting with a webcam showing the team’s information radiator and sending out an alert to everyone’s mobile telephone. As well as a reminder to call in, the alert also asks ‘Is there anything blocking or potentially blocking your progress?’ Which statement BEST explains how this approach applies the rich communication focus area? (Copyright © AXELOS Limited 2018, usage approved by AXELOS Limited. All rights reserved.)
Using the Project Scenario and Move Premises Additional information, answer the following question: Production line releases have been planned and the floor layout has been assigned to the four lines. At the end of Stage 3 the project board suggested that space is provided for a fifth production line because the project is turning out to be as successful as they had hoped. The project manager has suggested that release plans should complement the planning at the stage plan level in the future. Which BEST explains why this observation shows a good understanding of the frequent releases focus area? (Copyright © AXELOS Limited 2018, usage approved by AXELOS Limited. All rights reserved.)
5 Sterne |
|
5 |
4 Sterne |
|
0 |
3 Sterne |
|
0 |
2 Sterne |
|
0 |
1 Stern |
|
0 |