The lecture PRINCE2 Agile® Practitioner: Sample Exam (1) by Dion Training is from the course PRINCE2 Agile® – Practitioner 6th Edition including Exam (EN).
Which describes lean startup? (Copyright © AXELOS Limited 2018, usage approved by AXELOS Limited. All rights reserved.)
Which type of change should PRINCE2 Agile be used for? (Copyright © AXELOS Limited 2018, usage approved by AXELOS Limited. All rights reserved.)
Which describes an agile approach which can be integrated with PRINCE2 Agile? (Copyright © AXELOS Limited 2018, usage approved by AXELOS Limited. All rights reserved.)
Which describes the PRINCE2 method of project management according to the eight guidance points? (Copyright © AXELOS Limited 2018, usage approved by AXELOS Limited. All rights reserved.)
How might a PRINCE2 organization gain by using PRINCE2 Agile? (Copyright © AXELOS Limited 2018, usage approved by AXELOS Limited. All rights reserved.)
How does a delivery team ‘blend and weave’ PRINCE2 with agile ways of working? (Copyright © AXELOS Limited 2018, usage approved by AXELOS Limited. All rights reserved.)
Using the Project Scenario and Rebranding Additional Information, answer the following question: The ‘Chesterton’s Cheese? Yes please!’ project retrospective concluded that despite the campaign being successful, the company has a recognition problem in its non-English speaking markets. It was recommended that future campaigns make use of uniquely distinguishable branding. Which PRINCE2 principle being applied? (Copyright © AXELOS Limited 2018, usage approved by AXELOS Limited. All rights reserved.)
Using the Project Scenario and Rebranding Additional Information, answer the following question: The project manager has authorized the ‘Collateral’ work package which must be delivered by the end of Week 5. It includes the following requirements: • Corporate signage - Should Have; • Website look and feel - Must Have; • Letterheads - Must Have. The corporate signage is not thought to add as much value as the other products. Why does this represent a good application of the 'manage by exception' principle? (Copyright © AXELOS Limited 2018, usage approved by AXELOS Limited. All rights reserved.)
Using the Project Scenario and Rebranding Additional Information, answer the following question: A marketing campaign to promote Chesterton Blue will target a non-English speaking country in order to determine whether the proposed new corporate logo is sufficiently unique and recognizable. The senior user will approve the chosen logo. During Brand-u-Like’s most recent daily stand-up meeting, a number of observations were made. Which observation should be recorded as an item that that may potentially block the team’s progress? (Copyright © AXELOS Limited 2018, usage approved by AXELOS Limited. All rights reserved.)
Using the Project Scenario and Rebranding Additional Information, answer the following question: During Stage 4, the Cheese Marketing Association informed Brand-u-Like that Chesterton’s Cheese is allowed to use its quality accreditation logo as part of its branding on all of their marketing materials and products. How should this be managed by Brand-u-Like? (Copyright © AXELOS Limited 2018, usage approved by AXELOS Limited. All rights reserved.)
Using the Project Scenario and Rebranding Additional Information, answer the following question: It was recommended that a marketing campaign to promote Chesterton Blue is used to determine whether the proposed new corporate logo is sufficiently unique and recognizable. The customer subject matter expert (CSME) in the Brand-u-Like team has added this new marketing campaign to the Marketing Team’s product backlog. How effectively does this apply the change theme? (Copyright © AXELOS Limited 2018, usage approved by AXELOS Limited. All rights reserved.)
Using the Project Scenario and Rebranding Additional Information, answer the following question: During Brand-u-Like’s most recent daily stand-up meeting, a rumour that one of their suppliers may become insolvent was reported. As a result, it was agreed that a safe-to-fail experiment should be conducted to determine the likelihood of this occurring. How effectively does this apply the risk theme? (Copyright © AXELOS Limited 2018, usage approved by AXELOS Limited. All rights reserved.)
Using the Project Scenario and Rebranding Additional Information, answer the following question: The collateral work package is dependent upon the redesign of the corporate logo. In addition, the marketing campaign and ‘Story of Cheese’ are both dependent upon the outputs of the rebranding work. How should the Brand-u-Like team respond to this during the ‘accepting a work package’ stage? (Copyright © AXELOS Limited 2018, usage approved by AXELOS Limited. All rights reserved.)
Using the Project Scenario and Rebranding Additional Information, answer the following question: The products produced by Brand-u-Like will be delivered in stage 2 only. The project board has agreed to visit the board room to review the burn charts each week. Which reason BEST explains whether this is a suitable approach for the ’directing a project’ process? (Copyright © AXELOS Limited 2018, usage approved by AXELOS Limited. All rights reserved.)
Using the Project Scenario and Rebranding Additional Information, answer the following question: The project manager has worked with Brand-u-Like to create a work package which releases the collateral items in weeks 4 and 5. The stage plan shows the collateral items as a list in the form of a backlog. Brand-u-Like has produced a release backlog which covers two sprints each of one week duration. Which statement BEST explains why this approach is appropriate for the ‘managing product delivery’ process? (Copyright © AXELOS Limited 2018, usage approved by AXELOS Limited. All rights reserved.)
Using the Project Scenario and Rebranding Additional Information, answer the following question: At the start of the project the Agilometer was used and the ‘advantageous environmental conditions’ slider was set at a high level across all sliders and all work streams. When reviewing the project’s performance at the end of week 14, this was felt to have been too optimistic. Throughout the project it was found that Brand-u-Like was not willing to change their approach and would not commit to their work until it was fully documented and authorized. In which report should this information be included? (Copyright © AXELOS Limited 2018, usage approved by AXELOS Limited. All rights reserved.)
Using the Project Scenario and Rebranding Additional Information, answer the following question: When contributing to the development of the change control approach, Brand-u-Like wish to specify how changes to the detailed brief they have produced will be managed. They can then charge for changes made to it. Which reason BEST explains whether the change control approach should be used in this way? (Copyright © AXELOS Limited 2018, usage approved by AXELOS Limited. All rights reserved.)
Using the Project Scenario and Rebranding Additional Information, answer the following question: The acceptance criteria relating to the new logo have been set at a high level in the project product description (PPD). The introduction section of the quality management approach contains the objective of ensuring that this standard is achieved. Which BEST explains why this statement should be included in the introduction section of the quality management approach? (Copyright © AXELOS Limited 2018, usage approved by AXELOS Limited. All rights reserved.)
Using the Project Scenario and Marketing Campaign Additional Information, answer the following question: The Marketing Team believes that the most successful viral marketing videos are normally uploaded to YouTube® and shared by people using Twitter®. Videos on Facebook® have much less impact. Adding pictures from the video onto Instagram® could also improve the take-up rate. The acceptance criteria need to be set for where the video is made available. Which tolerance level is MOST suitable for the acceptance criteria, in order to comply with the ‘protect the level of quality’ target? (Copyright © AXELOS Limited 2018, usage approved by AXELOS Limited. All rights reserved.)
Using the Project Scenario and Marketing Campaign Additional Information, answer the following question: The Marketing Team is working on the advertisements in the first timebox but there is not enough time to complete them all. The remaining requirements to be completed for this timebox are: • Must have advertisements in the 'Good Food' and 'Great International Food' magazines; • Should have advertisements in 'Cook Organic' and 'The Vegetarian' magazines. How should the team respond, taking into account the 'five targets'? (Copyright © AXELOS Limited 2018, usage approved by AXELOS Limited. All rights reserved.)
Using the Project Scenario and Marketing Campaign Additional Information, answer the following question: The business case identifies that the marketing campaign must achieve a minimum of a 10% increase in sales within three months to be viable, and it would also like to achieve a wider awareness of Chesterton’s to improve their long-term sales. Two television advertisements should achieve the highest increase in awareness but the sales increase is forecast to be approximately 5%. A promotion in magazines is forecast to increase the overall sales by 12% in the short term but is not expected to improve awareness. The Marketing Team is assessing the compromise between the numbers of television advertisements to run against the promotion in magazines. How should the team respond taking into account the ‘five targets’? (Copyright © AXELOS Limited 2018, usage approved by AXELOS Limited. All rights reserved.)
Using the Project Scenario and Marketing Campaign Additional Information, answer the following question: The Marketing Team is planning the work for the first timebox in Stage 3. At the end of this two- week timebox, the following campaigns are planned to be released: • Social media - it is thought that this campaign will generate the greatest response from potential customers and is critical; • Newspaper - the target market for Chesterton's cheeses is thought to be strongly influenced by newspaper advertisements; • Radio - this is seen as less critical as radio advertisements are on local stations and reach a more restricted audience. The Marketing Team manager has identified that it will not be possible to deliver all of the above campaigns in the current timebox. As a result, the team manager has consulted the CSME and they have agreed that the radio campaign should be delayed until timebox 2 in the current stage. Which reason explains why the team manager should 'be on time and hit deadlines' rather than deliver the entire scope? (Copyright © AXELOS Limited 2018, usage approved by AXELOS Limited. All rights reserved.)
Using the Project Scenario and Marketing Campaign Additional Information, answer the following question: The project product description for the Golden Clog project includes the following acceptance criterion in relation to the marketing campaign: ‘The marketing campaign must accurately describe the ingredients and characteristics of the 5 most popular cheeses to generate enquiries about these cheeses at the International Cheese Festival.’ Which reason explains why the team manager should ‘protect the level of quality’ of the marketing campaign? (Copyright © AXELOS Limited 2018, usage approved by AXELOS Limited. All rights reserved.)
Using the Project Scenario and Marketing Campaign Additional Information, answer the following question: One purpose of the marketing campaign is to promote awareness of the Chesterton’s Blue cheese, using advertisements based on the smell of the cheese. There is a negative reaction from the public to the first advertisement. Further research identified that this is because the public dislikes the photographs of noses on the advertisement. The Marketing Team decide to immediately change from using photographs of noses to new ones based on smiling faces in the next timebox. Which BEST describes why this change complies with the ‘embrace change’ target? (Copyright © AXELOS Limited 2018, usage approved by AXELOS Limited. All rights reserved.)
Using the Project Scenario and Marketing Campaign Additional Information, answer the following question: The CSME on the Marketing Team who is responsible each day for updating social media for the Golden Clog project is on holiday during weeks 8-9. Brand-u-Like, who is rebranding Chesterton’s Cheese, has several trainees and has offered to transfer these trainees at a reduced rate to the Marketing Team to assist in this work. Why should the project manager resist this request in accordance with the ‘keep teams stable’ target? (Copyright © AXELOS Limited 2018, usage approved by AXELOS Limited. All rights reserved.)
Using the Project Scenario and Marketing Campaign Additional Information, answer the following question: The project is now in stage 4 and the marketing campaign has led to a significant increase in demand for a wider range of cheeses. However, the radio campaign was not delivered during stage 3 and at the current rate of progress it is unlikely that all of the following remaining campaigns will be delivered during the stage: • Radio; • Television; • Video sharing using social media. The CSME has confirmed that the video sharing is now seen as equally important to the other remaining campaigns and the Marketing Team should deliver everything from all three campaigns in the current timebox. Which reason explains how this applies the 'accept that the customer doesn't need everything' target? (Copyright © AXELOS Limited 2018, usage approved by AXELOS Limited. All rights reserved.)
Using the Project Scenario and website Additional information, answer the following question: Web&Go are working on the ordering timebox which includes: • Incorporating the new branding; • A cheese search and filter function; • A downloadable catalogue of cheeses. The most important deliverable for this timebox is to demonstrate how the new branding will be used on the website. How should the 'manage by exception' principle be applied to this work? (Copyright © AXELOS Limited 2018, usage approved by AXELOS Limited. All rights reserved.)
Using the Project Scenario and website Additional information, answer the following question: Web&Go is using a Kanban approach to delivery. The following three requirements have been specified on a backlog: 1. Change customer details - Effort: Large 2. Incorporate new branding - Effort: Large 3. Cheese catalogue download - Effort: Medium Note: Large effort - relates to a lead time of 10 days or more. Medium effort - relates to a lead time of 5 - 10 days. Web&Go has started work on all three requirements simultaneously. Why is this is a poor application of the 'focus on products' principle? (Copyright © AXELOS Limited 2018, usage approved by AXELOS Limited. All rights reserved.)
Using the Project Scenario and website Additional information, answer the following question: Web&Go is using Kanban to deliver the ordering work package in stage 3. How should the organization theme be tailored for this team? (Copyright © AXELOS Limited 2018, usage approved by AXELOS Limited. All rights reserved.)
Using the Project Scenario and website Additional information, answer the following question: The Web&Go team are delivering the ordering work package stage using a Kanban approach. The work package includes the following requirements: • Create an order for some cheese - Must have; • Change an existing open order that has been submitted - Should have; • Create a customer account/login - Must have. How should Web&Go estimate the delivery of this work package so that the plans theme is tailored appropriately? (Copyright © AXELOS Limited 2018, usage approved by AXELOS Limited. All rights reserved.)
Using the Project Scenario and website Additional information, answer the following question: When preparing the business case, the project manager asked Web&Go to estimate the effort required for the customer account/login function. Web&Go has been asked to provide estimates based on a best-case scenario for each of the following: • Customer name, title and gender; • Delivery address and delivery preferences e.g. time of day; • Billing address; • Contact details including email, home telephone, work telephone and mobile/cell phone; • Password and 'forgot my password'. What BEST explains how this approach tailors the business case theme? (Copyright © AXELOS Limited 2018, usage approved by AXELOS Limited. All rights reserved.)
Using the Project Scenario and website Additional information, answer the following question: The IT team is using a burn-down chart for the Story of Cheese work package. The line showing the amount of work done is above the line showing the ideal rate of progress and is relatively flat. The IT team manager concluded that the focus should now be on incorporating the new branding onto the website and the history of Chesterton’s for the remainder of the timebox. Other, lower priority, requirements are not going to be delivered as a result. What BEST explains why this response to the burn-down chart tailors the progress theme well? (Copyright © AXELOS Limited 2018, usage approved by AXELOS Limited. All rights reserved.)
Using the Project Scenario and website Additional information, answer the following question: A business analyst has been collecting ideas from sales staff on ways to improve the sales process. These ideas have been collated onto a backlog. This list of possible changes is being discussed during the ‘starting up a project’ process along with other ideas to be included in the project. The value of each of these ideas needs to be understood by the members of the project board. How should the project management team BEST present the project brief to the project board in order to achieve this? (Copyright © AXELOS Limited 2018, usage approved by AXELOS Limited. All rights reserved.)
Using the Project Scenario and website Additional information, answer the following question: At the end of week 14, the project manager is getting ready to complete the ‘closing a project’ process. The rebranding, marketing and premises move have all been completed. The website is now fully operational and the project manager wants to review how well the project has delivered the website in order to pass on lessons to future projects. How should the project manager complete the ‘closing a project’ process? (Copyright © AXELOS Limited 2018, usage approved by AXELOS Limited. All rights reserved.)
Using the Project Scenario and website Additional information, answer the following question: At the end of week 7, the first timebox relating to the ordering on the website has been completed. The Web&Go team manager has been planning a retrospective with an independent facilitator. They have spent two hours planning with the following conclusions: • All team members working on the ordering work package stage (including staff from Web&Go) should attend as well as the project manager; • At the retrospective, the focus should be on establishing how rich communication has contributed to a successful delivery of the timebox and how it should be used going forward. Which BEST explains how well this tailors the ‘controlling a stage’ process? (Copyright © AXELOS Limited 2018, usage approved by AXELOS Limited. All rights reserved.)
Using the Project Scenario and website Additional information, answer the following question: Web&Go are working on the payment timebox. The timebox includes the following requirements: • Secure payment - Must have; • Allow payment by credit card/debit card - Must have; • Allow payment by PayPal - Should have. How should Web&Go start delivering the team plan where the work in progress (WIP) limit on the build column of the Kanban board is 2? (Copyright © AXELOS Limited 2018, usage approved by AXELOS Limited. All rights reserved.)
Using the Project Scenario and website Additional information, answer the following question: During stage 4, work on the Story of Cheese is due to commence. The IT team are delivering this work package which includes the following requirements: • Incorporation of the new branding; • History of cheese; • History of Chesterton’s. How should the work package for this timebox be authorized? (Copyright © AXELOS Limited 2018, usage approved by AXELOS Limited. All rights reserved.)
Using the Project Scenario and website Additional information, answer the following question: The following risk has been identified during the assessment of the Agilometer and entered into the risk register. The risk register is displayed on the information radiator in the board room. ‘As Web&Go are using a Kanban approach and the IT Team are using a basic agile approach using different terminology, there is a risk that it may result in poor communication, leading to the failure to integrate the products effectively into a single, coherent website.’ What BEST explains how this tailors the risk register? (Copyright © AXELOS Limited 2018, usage approved by AXELOS Limited. All rights reserved.)
Using the Project Scenario and Move Premises Additional Information, answer the following question: The project manager used the Agilometer to assess the prevailing agile environment in order to tailor PRINCE2 in the most effective way. Due to the current production processes being located over several sites and the landlord of the new premises being in a time zone of over ten hours difference, it was observed that the ‘Ease of Communication’ slider is low. Which action is an appropriate response to this observation? (Copyright © AXELOS Limited 2018, usage approved by AXELOS Limited. All rights reserved.)
Using the Project Scenario and Move Premises Additional Information, answer the following question: The premises team is made up of both operations and maintenance staff, assigned full-time to the team. The operations process must comply with hygiene regulations and therefore the operations staff is focused on delivering the required level of quality. The operations staff members feel that only they have the authority and knowledge to make the key decisions with respect to how the lines are set-up. They are unhappy that the maintenance staff members have, in the past, not appropriately implemented some minor operational requirements. Which slider on the Agilometer would be MOST appropriate to give a low setting as a result of this behaviour? (Copyright © AXELOS Limited 2018, usage approved by AXELOS Limited. All rights reserved.)
Using the Project Scenario and Move Premises Additional Information, answer the following question: The following requirement has been specified for the moving of premises: As the operations manager responsible for all of the production lines; • I want to have the production lines for all cheeses sold by Chesterton’s to be located on one site, alongside the office functions; • So that efficiencies can be achieved by managing staff and deliveries from a single location. What is the MOST appropriate way to record this wording? (Copyright © AXELOS Limited 2018, usage approved by AXELOS Limited. All rights reserved.)
Using the Project Scenario and Move Premises Additional Information, answer the following question: The high-level requirement for the main store for the cheese is that it MUST be kept at a constant temperature of at least 10 °C. The cooling unit to achieve this temperature is much more expensive than expected so the requirement was revisited. Not all the cheeses need to be stored at the same temperature. Which approach should be taken to deal with this issue? (Copyright © AXELOS Limited 2018, usage approved by AXELOS Limited. All rights reserved.)
Using the Project Scenario and Move Premises Additional Information, answer the following question: The choice and order of which production line to move to the new premises may be affected by which cheeses Chesterton’s decide to promote at the International Cheese Festival. Which is the MOST appropriate way to convey the impact that this decision has on the premises team? (Copyright © AXELOS Limited 2018, usage approved by AXELOS Limited. All rights reserved.)
Using the Project Scenario and Move Premises Additional Information, answer the following question: The move of the first production line to the new premises has been completed. Which feedback would be MOST useful according to the frequent releases focus area? (Copyright © AXELOS Limited 2018, usage approved by AXELOS Limited. All rights reserved.)
Using the Project Scenario and Move Premises Additional Information, answer the following question: The project manager used the Agilometer to assess the ‘move premises’ work stream. The Agilometer scored low for all sliders. The project manager then discussed the results of the Agilometer further with the team moving premises and discovered that the team is cautious in its approach. They want to obtain sign-off of the technical design for all production lines before moving any of them. The design needs to include many mandatory hygiene, health and safety requirements. The team then wants to move and test each production line, one by one. Which slider should the project manager set higher as a result of this discussion? (Copyright © AXELOS Limited 2018, usage approved by AXELOS Limited. All rights reserved.)
Using the Project Scenario and Move Premises Additional Information, answer the following question: The premises team has just been appointed and is made up of operations and facilities staff. Which characteristic justifies a high-level setting for the ‘ease of communication’ slider on the Agilometer for this part of the project? (Copyright © AXELOS Limited 2018, usage approved by AXELOS Limited. All rights reserved.)
Using the Project Scenario and Move Premises Additional Information, answer the following question: As a: production line worker; I want to: be able to transport the cheese into the refrigeration room located at the end of each production line; So that: the time needed to move the cheese into the refrigeration room is as short as possible. Which explains whether any part of this user story is appropriate? (Copyright © AXELOS Limited 2018, usage approved by AXELOS Limited. All rights reserved.)
Using the Project Scenario and Move Premises Additional Information, answer the following question: Twenty-two requirements have been identified for the cheese dispatch process, broken down by number as follows: • Weighing cheeses - 2 • Wrapping cheeses - 2 • Labelling cheeses - 2 • Packing dispatch box - 4 • Weighing dispatch box - 2 • Addressing the dispatch box - 7 • Applying postage to dispatch box - 3 Which stage would the premises team MOST likely be in if they were applying the requirements focus area correctly? (Copyright © AXELOS Limited 2018, usage approved by AXELOS Limited. All rights reserved.)
Using the Project Scenario and Move Premises Additional Information, answer the following question: The premises team has decided to mark-out the production lines with cardboard boxes on the production room floor to validate that the production lines will fit. Which BEST explains why this approach is a good application of the rich communication focus area? (Copyright © AXELOS Limited 2018, usage approved by AXELOS Limited. All rights reserved.)
Using the Project Scenario and Move Premises Additional Information, answer the following question: The premises team has planned to move the production lines one-by-one over a series of timeboxes, rather than moving all lines at the same time in the last timebox. However, this approach means that the deliveries of ingredients and packaging and the dispatching the produced cheeses will be difficult to coordinate. Which statement BEST explains how this approach applies the frequent releases focus area? (Copyright © AXELOS Limited 2018, usage approved by AXELOS Limited. All rights reserved.)
5 Stars |
|
5 |
4 Stars |
|
0 |
3 Stars |
|
0 |
2 Stars |
|
0 |
1 Star |
|
0 |