The lecture PRINCE2 Agile® Foundation: Sample Exam (1) by Dion Training is from the course PRINCE2 Agile® – Foundation 6th Edition including Exam (EN).
Which is a PRINCE2 principle? (Copyright © AXELOS Limited 2021, usage approved by AXELOS Limited. All rights reserved.)
Which is a purpose of the risk theme? (Copyright © AXELOS Limited 2021, usage approved by AXELOS Limited. All rights reserved.)
Which is a purpose of the 'managing a stage boundary' process? (Copyright © AXELOS Limited 2021, usage approved by AXELOS Limited. All rights reserved.)
What is the project product description used for during the 'closing a project' process? 1. To validate that acceptance criteria have been achieved. 2. To check that the project has delivered what is expected. 3. To identify lessons learned throughout the project delivery. 4. To validate any benefits that have been realized so far. (Copyright © AXELOS Limited 2021, usage approved by AXELOS Limited. All rights reserved.)
Which responsibilities are specifically assigned to the team manager? 1. Ensuring that the required products are produced appropriately. 2. Delivering products within the time, cost and quality tolerances. 3. Representing the interests of those using the project's products. 4. Being accountable for the technical integrity of the whole project. (Copyright © AXELOS Limited 2021, usage approved by AXELOS Limited. All rights reserved.)
Which is a typical characteristic of project work? (Copyright © AXELOS Limited 2021, usage approved by AXELOS Limited. All rights reserved.)
Which statement defines Scrum? (Copyright © AXELOS Limited 2021, usage approved by AXELOS Limited. All rights reserved.)
Which statement describes PRINCE2, according to the eight guidance points in PRINCE2 Agile? (Copyright © AXELOS Limited 2021, usage approved by AXELOS Limited. All rights reserved.)
How does PRINCE2 Agile refer to the term 'agile'? (Copyright © AXELOS Limited 2021, usage approved by AXELOS Limited. All rights reserved.)
Which TWO statements about the customer representative are CORRECT? 1. They review the project's products when needed. 2. They explain what alternatives there are to satisfy individual requirements. 3. They ensure that work complies with organizational standards. 4. They contribute specific information that may be of use to the project. (Copyright © AXELOS Limited 2021, usage approved by AXELOS Limited. All rights reserved.)
Which explains how the 'defined roles and responsibilities' principle is applied in an agile context? (Copyright © AXELOS Limited 2021, usage approved by AXELOS Limited. All rights reserved.)
How is the 'tailor to suit the project' principle applied in an agile context? (Copyright © AXELOS Limited 2021, usage approved by AXELOS Limited. All rights reserved.)
Which statement about the PRINCE2 Agile behaviour 'collaboration' is CORRECT? (Copyright © AXELOS Limited 2021, usage approved by AXELOS Limited. All rights reserved.)
Which statement explains the PRINCE2 Agile behaviour of 'rich communication'? (Copyright © AXELOS Limited 2021, usage approved by AXELOS Limited. All rights reserved.)
What would describe a set of criteria used to determine if a piece of work can be started? (Copyright © AXELOS Limited 2021, usage approved by AXELOS Limited. All rights reserved.)
When tailoring the business case theme, what situation does the approach 'taking a leap of faith' refer to? (Copyright © AXELOS Limited 2021, usage approved by AXELOS Limited. All rights reserved.)
What is used as contingency on a PRINCE2 Agile project? (Copyright © AXELOS Limited 2021, usage approved by AXELOS Limited. All rights reserved.)
Which statement about the synchronization between the PRINCE2 project management structure and the agile delivery-based roles is CORRECT? (Copyright © AXELOS Limited 2021, usage approved by AXELOS Limited. All rights reserved.)
What is the primary source of information, with respect to progress? (Copyright © AXELOS Limited 2021, usage approved by AXELOS Limited. All rights reserved.)
In terms of risk, what BEST describes the agile way of working? (Copyright © AXELOS Limited 2021, usage approved by AXELOS Limited. All rights reserved.)
In which situation should an empowered self-organizing team, working at the delivery level, be free to handle change dynamically? (Copyright © AXELOS Limited 2021, usage approved by AXELOS Limited. All rights reserved.)
Which should take place within the 'controlling a stage' process? (Copyright © AXELOS Limited 2021, usage approved by AXELOS Limited. All rights reserved.)
After the 'starting up a project' process, in which process is the Agilometer FIRST used? (Copyright © AXELOS Limited 2021, usage approved by AXELOS Limited. All rights reserved.)
What is the focus of the regular reports that are received by the project board? (Copyright © AXELOS Limited 2021, usage approved by AXELOS Limited. All rights reserved.)
Which is the BEST way to close a PRINCE2 Agile project? (Copyright © AXELOS Limited 2021, usage approved by AXELOS Limited. All rights reserved.)
Which statements about the typical tailoring of a project product description in an agile environment are CORRECT? 1. It should be produced collaboratively with the wider project management team as part of a workshop. 2. It should focus on how the end product of the project will deliver the desired outcomes. 3. It should focus on how the benefits will be enabled through iterative development. 4. It should define the techniques to be used to accommodate the agile ways of communicating. (Copyright © AXELOS Limited 2021, usage approved by AXELOS Limited. All rights reserved.)
Which statement explains the setting of the benefit tolerance for a project in an agile context? (Copyright © AXELOS Limited 2021, usage approved by AXELOS Limited. All rights reserved.)
Which statement about the 'embrace change' target is CORRECT? (Copyright © AXELOS Limited 2021, usage approved by AXELOS Limited. All rights reserved.)
Which statement explains the target 'keep teams stable' for flexible delivery? (Copyright © AXELOS Limited 2021, usage approved by AXELOS Limited. All rights reserved.)
Which statement explains the target 'be on time and hit deadlines' for flexible delivery? (Copyright © AXELOS Limited 2021, usage approved by AXELOS Limited. All rights reserved.)
Which statement about the 'accept that the customer doesn't need everything' target is CORRECT? (Copyright © AXELOS Limited 2021, usage approved by AXELOS Limited. All rights reserved.)
Which statement about the 'protect the level of quality' target is CORRECT? (Copyright © AXELOS Limited 2021, usage approved by AXELOS Limited. All rights reserved.)
Which term defines the complete list of new features for a project? (Copyright © AXELOS Limited 2021, usage approved by AXELOS Limited. All rights reserved.)
Which agile term has a similar meaning to the term 'benefits' in PRINCE2? (Copyright © AXELOS Limited 2021, usage approved by AXELOS Limited. All rights reserved.)
What is timeboxing? (Copyright © AXELOS Limited 2021, usage approved by AXELOS Limited. All rights reserved.)
Which is a CORRECT statement with reference to epics? (Copyright © AXELOS Limited 2021, usage approved by AXELOS Limited. All rights reserved.)
Which describes an information radiator? (Copyright © AXELOS Limited 2021, usage approved by AXELOS Limited. All rights reserved.)
Which does NOT describe a Scrum team? (Copyright © AXELOS Limited 2021, usage approved by AXELOS Limited. All rights reserved.)
How should a workshop ideally be run? (Copyright © AXELOS Limited 2021, usage approved by AXELOS Limited. All rights reserved.)
What is used to display the progress of a delivery team using lines plotted on a graph? (Copyright © AXELOS Limited 2021, usage approved by AXELOS Limited. All rights reserved.)
Why should Lean Startup be applied to a PRINCE2 project? (Copyright © AXELOS Limited 2021, usage approved by AXELOS Limited. All rights reserved.)
What is the recommended way to prepare agile estimates? (Copyright © AXELOS Limited 2021, usage approved by AXELOS Limited. All rights reserved.)
Which is a purpose of a retrospective? (Copyright © AXELOS Limited 2021, usage approved by AXELOS Limited. All rights reserved.)
How should the delivery team's working agreements be created? (Copyright © AXELOS Limited 2021, usage approved by AXELOS Limited. All rights reserved.)
How is a user story typically recorded? (Copyright © AXELOS Limited 2021, usage approved by AXELOS Limited. All rights reserved.)
What is indicated if a slider score on the Agilometer is lower than its score on the previous assessment? (Copyright © AXELOS Limited 2021, usage approved by AXELOS Limited. All rights reserved.)
Which slider in the Agilometer would be MOST impacted by how closely the project's participants are located? (Copyright © AXELOS Limited 2021, usage approved by AXELOS Limited. All rights reserved.)
Who should be involved in establishing release plans? (Copyright © AXELOS Limited 2021, usage approved by AXELOS Limited. All rights reserved.)
Which is an objective of the rich communication focus area? (Copyright © AXELOS Limited 2021, usage approved by AXELOS Limited. All rights reserved.)
Which factor defines whether MoSCoW or an 'ordering' approach to requirements prioritization should be followed? (Copyright © AXELOS Limited 2021, usage approved by AXELOS Limited. All rights reserved.)
5 Stars |
|
5 |
4 Stars |
|
0 |
3 Stars |
|
0 |
2 Stars |
|
0 |
1 Star |
|
0 |